Almost every MVP requirements list we receive is an eight-month project. That is normal: the client is describing the product as it should eventually be. The job of discovery is to find, inside that description, the shortest version that already tests the main hypothesis.
The scenario first, features second
We do not prioritise a list of functions — we pick one end-to-end scenario and take it all the way. For a marketplace that is “the buyer finds a product, agrees the price and places the order”; everything outside it moves to version two, however simple it looks.
The awkward part of this approach is that it produces a narrow product: one role, one path, minimal settings. The payoff is that in week ten it can genuinely be used, instead of showing half the screens of every part of the system.
What we cut almost every time
- A five-role permission model — two roles are enough for an MVP, the rest take a sprint later
- Settings and builders — until the scenario is validated there is nothing to configure
- An admin panel “for every occasion” — the first month of operations is cheaper to cover with scripts
- A second interface language and a second platform — twice the work for the same hypothesis
- Reports nobody requested by name: every report needs an owner
On our last six projects this list absorbed between 25 and 40% of the original requirements. One detail matters: we do not delete them, we move them into an explicit “second release” — which makes the decision look like sequencing rather than refusal.
What must never be cut
Four things always come back as a rewrite if you economise on them: authentication and access control, anything touching money and personal data, product analytics, and automated deployment. The first two because holes in them are never “finished later”, the third because without it the hypothesis cannot be tested, the fourth because manual releases eat weeks where the schedule counts in days.
“An MVP is not a cheap version of the product, it is a complete product with a very narrow scope. The difference is what gets cut: quality or coverage.”
What ten weeks look like
Two weeks for discovery and a prototype, six for five development sprints with a demo every two weeks, and two for stabilisation, load checks and launch to real users. The team: four engineers, a half-time analyst and a designer for the first three weeks.
The main risk to that schedule is not technical — it is decision-making on the client's side. If the answer to “which of the two approval flows do we take” arrives a week later, the deadline moves by a week. That is why we fix response times in the contract and keep one person with the authority to decide. How this works inside a sprint is covered in our article on demos every two weeks.